King West 65-Unit Furnished Rental Building Magic-Pak HWC to MGE Replacement
A documented project record from Condo HVAC Repair Toronto. A 1996 King West building running as a 65-unit furnished corporate rental was averaging 10-12 Magic-Pak failures per year. The replacement program ran floor-by-floor over 6 weeks with zero displaced guests, scheduled around real-time booking data.
By The Condo HVAC Repair Toronto Crew
Project Attributes
- Scope
- 65 Magic-Pak HWC series PTACs replaced with MGE series over 6 weeks with zero displaced guests
- Price
- $287,500 CAD
- Payment
- 15% deposit, weekly progress, 10% retention
- Lead time
- 6 weeks (MGE manufacturer lead time)
- On site
- 6 consecutive weeks on-site
- Client
- Corporate rental operator (1996 building)
- Crew
- Marcus Chen (Ops Mgr) + 3-tech crew + guest coordinator
- Equipment
- Magic-Pak HWC → MGE series + 12 louver reframes
- Neighbourhood
- King West
- Building
- 65 suites, 1996 construction
The Challenge
A 1996 King West furnished corporate rental building was logging 10-12 Magic-Pak HWC failures per year across 65 suites. Each failure meant a displaced guest, a 2-3 day turnaround, and a potential liability on the booking platform.
The operations director needed a floor-by-floor replacement with zero displaced guests as a non-negotiable requirement.
Results
- All 65 units replaced across 6 weeks with zero displaced guests.
- 100% guest acceptance on 12 in-stay coordination requests.
- Approximately 15% reduction in combined heating and cooling energy use post-replacement.
- Zero commissioning failures, zero guest complaints during or after program.
How We Ran It
- 1
Real-time booking coordination
Operations team shared live booking data. 53 of 65 units were scheduled into natural check-out windows (3+ hour vacancies). The remaining 12 were coordinated directly with in-stay guests at mutually convenient times.
- 2
Floor-by-floor rolling swap
Six weeks on-site, 11 units per week, working top-floor-down in 2-floor increments. 90-minute install window per suite with 4-technician crew.
- 3
Louver reframing for MGE profile
MGE chassis required slightly wider exterior louver on 12 of 65 units. Louvers reframed with new weatherstripping as part of the swap sequence.
- 4
New 24V thermostats and commissioning
Every suite received a new 24V thermostat for MGE compatibility plus 15-minute heat and cool verification before sign-off.
Project Photos
Click any photo to enlarge it.
"Not a single guest was displaced. The MGE units run quieter than the HWCs ever did and our utility bills are down about 15 percent since the swap."
Daniel K., Operations director, corporate rental
More Condo HVAC Projects
Yorkville Yorkville 42-Unit Tower
Annual Fan Coil Service Program
- Scope
- 42 coil descales + 4 pumps + 11 valves
- On site
- 3 service nights across 2 weeks
- Crew
- Marcus Chen (Ops Mgr) + 4 technicians
- Equipment
- McQuay vertical fan coils, 2001 vintage
- Neighbourhood
- Yorkville
Mimico Mimico 180-Unit Lakefront
Building-Wide Fan Coil Replacement
- Scope
- Rolling fan coil replacement
- On site
- 14-week rolling install
- Crew
- Elena Vargas (Ops Mgr) + 2 crews
- Equipment
- Replacement vertical fan coils with ECM motors
- Neighbourhood
- Mimico
Downtown Markham Downtown Markham 24-Unit Mid-Rise
Water-Source Heat Pump Repair
- Scope
- Reversing valves + contactors
- On site
- 6 days over one season
- Crew
- James Kowalski (Ops Mgr) + 2 technicians
- Equipment
- Trane Axiom water-loop heat pumps
- Neighbourhood
- Downtown Markham
Planning Work Like This in Your Building?
Start with a free walk-through and readings in sample suites. Your board gets a written scope, per-unit pricing and a schedule before anyone commits.
- Written scope before work
- TSSA + Enbridge Red Tag + ESA + WSIB
- Written workmanship warranty