Condo HVAC Replacement | Thornhill

Thornhill 220-Unit Luxury Tower Water-Source Heat Pump Replacement Program

A documented project record from Condo HVAC Repair Toronto. A 1992 Thornhill luxury tower reached end-of-life on 220 original Trane Axiom heat pumps. Our 32-week rolling program replaced all 220 units with ClimateMaster Tranquility 30 chassis, including per-suite slide-out rail modifications for the slightly wider footprint. Zero residents displaced.

By The Condo HVAC Repair Toronto Crew

$945,000 CAD 32 consecutive weeks on-site + 1 week buffer 220 suites
ClimateMaster Tranquility chassis staged for Thornhill program install

Project Attributes

Scope
220 Trane Axiom water-source heat pumps replaced with ClimateMaster Tranquility 30 over 32 weeks with chassis slide-out rail modifications
Price
$945,000 CAD
Payment
10% deposit, monthly progress, 10% retention
Lead time
12 weeks (ClimateMaster manufacturer + rail modification engineering)
On site
32 consecutive weeks on-site + 1 week buffer
Client
Condo board + reserve fund consultant (1992 luxury tower)
Crew
Rachel Simard (Ops Mgr) + 5-tech crew + chassis specialist + resident coordinator
Equipment
Trane Axiom → ClimateMaster Tranquility 30 water-source heat pumps + Belimo zone valves
Neighbourhood
Thornhill
Building
220 suites, 1992 construction

The Challenge

A 1992 Thornhill luxury tower reached critical mass on failures of 220 original Trane Axiom water-source heat pumps. Reserve fund study flagged 2026-2028 as the replacement window.

Many owners had been in-suite 20+ years. The board required a replacement program with resident accommodation that matched the Thornhill community’s expectation of discretion and courtesy. The ClimateMaster Tranquility 30 replacement chassis also needed per-suite slide-out rail modifications because of a 1.5-inch wider footprint.

Results

  • All 220 units replaced on schedule across 32 weeks.
  • Zero resident displacement, zero commissioning failures.
  • Approximately 18% reduction in combined heating and cooling consumption (90-day post-install monitoring).
  • Board approved Phase 2 (common area + mechanical refresh) at first post-completion review.

How We Ran It

  1. 1

    Thirty-two-week rolling install

    Seven units per week over 32 consecutive weeks, Monday through Thursday with Fridays reserved for punch list and buffer. 72-hour advance written notice per suite plus morning-of knock reminder.

  2. 2

    Resident accommodation protocol

    Fourteen residents requested specific weekday windows for cultural or scheduling reasons. All 14 accommodations honored. Resident coordinator phone line staffed Monday-Friday 8 AM-6 PM throughout.

  3. 3

    Chassis slide-out rail modification

    Each suite closet rail cut and re-mounted 1.5 inches wider using matching galvanized angle iron. Cardboard template confirmed clearance before cutting. New ClimateMaster chassis slid in on new rails.

  4. 4

    Per-unit commissioning

    Refrigerant charge verified, loop flow tested, 15-minute heat and cool cycle before sign-off per suite. Belimo zone valves and 24V thermostats replaced at the same time.

Project Photos

Click any photo to enlarge it.

"Rachel ran a replacement program that respected the character of this building. The residents are long-time owners and they got courtesy and craftsmanship."

Michael B., Board president, Thornhill luxury tower

24-Hour Condo Emergency Dispatch

Planning Work Like This in Your Building?

Start with a free walk-through and readings in sample suites. Your board gets a written scope, per-unit pricing and a schedule before anyone commits.

  • Written scope before work
  • TSSA + Enbridge Red Tag + ESA + WSIB
  • Written workmanship warranty
Call (437) 523-7002 Book $185 Diagnostic